Tianjin "Coal to Power" Construction Project completed to benefit 460000 households

| gov.cn

Xinhua News Agency, Tianjin, 6 Nov (Reporter Mao Zhenhua)-- Tianjin has helped to control air pollution in the Beijing-Tianjin-Hebei region, and Tianjin has accelerated the pace of "changing coal to electricity." Up to now, the Tianjin area "coal to electricity" construction project has been completed, one year ahead of schedule to complete the clean heating "coal to electricity" power grid supporting construction and transformation tasks, benefiting 460000 households.

Recently, a 110 kV substation in Tianjin Jinghai District was put into operation, marking the successful completion of the "coal to electricity" task of the Tianjin Jinghai Power supply Company. This winter, Jinghai District will have 69466 households to enjoy the convenience of clean heating.

Chen Hongli, director of the Construction Department of Jinghai Power supply Company, which is responsible for supervising power transmission, said that the "coal to electricity" project involves 135 villages in Jinghai District, of which 31032 households in 66 villages are centralized, and 38434 households in 69 villages are distributed. It is necessary to build and expand 11 substations of 35 kV and above, 113km of transmission lines and more than 2000 km of distribution lines of 10kV and below, so as to fully ensure the demand for "coal to electricity" load. Jinghai power supply is speeding up the pace to ensure that construction is completed in the run-up to the heating season.

This year, the entire Tianjin "coal to electricity" construction project involved a total of 225500 households in 707 villages. The national network Tianjin Electric Power Company strengthens the supporting construction of the power network from the main network to the distribution network in an all-round way. A total of 51 new "coal to electricity" supporting power grid infrastructure projects have been built, with an additional substation capacity of 8.03 million KVA and a new line length of 800km. The power supply capacity of each line has been greatly strengthened, and the power grid structure has been significantly improved.

The relevant person in charge of Tianjin Electric Power of the National Power Grid said that in order to ensure the warm winter of "coal to electricity" users, the electric power department has taken differential operation and maintenance measures for the power supply lines of electric heating users, and implemented "restoring electricity first and then rush repair." Ensure that equipment failure disposal is in place in a timely manner and does not affect the heating of the masses.

Tianjin "Coal to Power" Construction Project completed to benefit 460000 households

| gov.cn

Xinhua News Agency, Tianjin, 6 Nov (Reporter Mao Zhenhua)-- Tianjin has helped to control air pollution in the Beijing-Tianjin-Hebei region, and Tianjin has accelerated the pace of "changing coal to electricity." Up to now, the Tianjin area "coal to electricity" construction project has been completed, one year ahead of schedule to complete the clean heating "coal to electricity" power grid supporting construction and transformation tasks, benefiting 460000 households.

Recently, a 110 kV substation in Tianjin Jinghai District was put into operation, marking the successful completion of the "coal to electricity" task of the Tianjin Jinghai Power supply Company. This winter, Jinghai District will have 69466 households to enjoy the convenience of clean heating.

Chen Hongli, director of the Construction Department of Jinghai Power supply Company, which is responsible for supervising power transmission, said that the "coal to electricity" project involves 135 villages in Jinghai District, of which 31032 households in 66 villages are centralized, and 38434 households in 69 villages are distributed. It is necessary to build and expand 11 substations of 35 kV and above, 113km of transmission lines and more than 2000 km of distribution lines of 10kV and below, so as to fully ensure the demand for "coal to electricity" load. Jinghai power supply is speeding up the pace to ensure that construction is completed in the run-up to the heating season.

This year, the entire Tianjin "coal to electricity" construction project involved a total of 225500 households in 707 villages. The national network Tianjin Electric Power Company strengthens the supporting construction of the power network from the main network to the distribution network in an all-round way. A total of 51 new "coal to electricity" supporting power grid infrastructure projects have been built, with an additional substation capacity of 8.03 million KVA and a new line length of 800km. The power supply capacity of each line has been greatly strengthened, and the power grid structure has been significantly improved.

The relevant person in charge of Tianjin Electric Power of the National Power Grid said that in order to ensure the warm winter of "coal to electricity" users, the electric power department has taken differential operation and maintenance measures for the power supply lines of electric heating users, and implemented "restoring electricity first and then rush repair." Ensure that equipment failure disposal is in place in a timely manner and does not affect the heating of the masses.



Li Keqiang's speech at the 14th East Asia Summit
Since its establishment 14 years ago, the East Asia Summit has become an important platform for dialogue and cooperation between countries within and outside the region. The summit, which brings together 18 countries, including major economies in the...




Li Keqiang attends 14th East Asia Summit
Li Keqiang pointed out that the East Asia Summit should adhere to the positioning of the "leader-led strategic forum" at the beginning of its establishment, balance political and security cooperation with social and economic development, strategic...



Look at the "Shanghai sample" of the Business Environment
"Super speed" is well deserved. Tesla's feelings were confirmed by the Global Business Environment report 2020 released by the World Bank on 24 October. Among the 190 economies in the world, China scored a total of 77.9 points in the business...




















Li Keqiang returns to Beijing from his visit
On the 5th, after attending the 18th meeting of the Council of Heads of Government (Prime Ministers) of the Shanghai Cooperation Organization (SCO), State Council Premier Li Keqiang paid an official visit to Uzbekistan, attended a series of East Asian...

Li Keqiang and Thai Prime Minister Prayuth meet with reporters
The prime ministers of the two countries made positive comments on the new achievements made in Sino-Thai cooperation. Li Keqiang said that Thailand is a good friend and partner of China's equality and mutual benefit. The two sides have strong...

Li Keqiang holds talks with Thai Prime Minister Prayuth
Li Keqiang congratulated Thailand on successfully hosting a series of meetings of leaders of East Asian cooperation. He said that China and Thailand are close and friendly neighbors, and bilateral relations have always developed healthily and...